Construction Activities for the Week of April 25

HERE is a link to Construction Activities on the University of Oregon New Residence Hall for the week of April 25 – April 29.

Construction activities for this week will consist of excavation with concrete commencing by the end of the week. An excavator and dump truck will work to haul debris and dirt off-site. Once concrete commences, concrete trucks and concrete pumps will help to place the concrete in the formwork.

Advertisements

Construction Activities for the Week of April 18

HERE is a link to Construction Activities on the University of Oregon New Residence Hall for the week of April 18 – April 22.

Construction activities for this week will consist of excavation with concrete commencing by the end of the week. An excavator and dump truck will work to haul debris and dirt off-site. Once concrete commences, concrete trucks and concrete pumps will help to place the concrete in the formwork.