Construction Activities for the Week of May 15 – May 19

Here is a link to Construction Activities on the University of Oregon New Residence Hall for the week of May 15 – May 19.  We will continue to have activity along Columbia and 17th as we pour curbs and sidewalks and work on landscaping. 

A portion of the sidewalk between our site and Global scholars gets cut out and replaced.  We plan to remove and re-pour it mid-next week.  That sidewalk will be closed off connecting Columbia to Moss during that time as we form it up.  Please plan on taking different routes during that time (see below for a picture of the area).

 

Advertisements

Construction Activities May 1 – May 5

Here is a link to Construction Activities on the University of Oregon New Residence Hall for the week of May 1 – May 5. We will be pouring site walls and starting sidewalks along Columbia and 17th.  This will require a concrete truck to be in these streets when we pour.  The truck will have a flagger with them to help keep traffic moving.  Thanks for your patience on this increased activity as we work around the site.